PA Workplan Upload Copy link

Description

Categories
Enginatics, R12 only, Upload
Repository
GitHub
Creates, updates and deletes the resource assignments of workplan tasks as on the Projects HTML workplan pages (Workplan > Tasks > Task Assignments), using pa_task_assignments_pub.

The assignments are maintained on the current working workplan version, or on the published version when workplan versioning is disabled for the project. Planning resources come from the resource list of the workplan plan type. Planned cost of a rate based resource is calculated from the planned quantity.

The resource of an existing assignment cannot be changed: delete the assignment and create a new one. Publish Workplan publishes the workplan version once all rows of the project uploaded successfully.

SQL 54 lines

Parameters 4

ParameterTypeList of values SQL
Upload ModeLOV
Operating UnitLOV
haouv.name=:p_operating_unit
Project NumberLOV
ppa.segment1=:p_project_number
Task NumberLOV
ppe.element_number=:p_task_number